Timeline, status and deliverables dashboard
Run Consolidation
Target date: 15 Aug 2026
Total Tasks
15
Completed
6
In Progress
1
Pending
7
Holding company and its subsidiaries
Each bar shows a task duration between Jun 1 and Aug 15, 2026.
| Phase | # | Task | Responsibility | From | To | Duration | Status | Notes |
|---|---|---|---|---|---|---|---|---|
| Phase 1 | 1 | Finalize COA | HITS | 01 Jun | 09 Jun | 9d | Done | Chart of Accounts approved |
| 2 | Initial Configuration | HITS | 10 Jun | 14 Jun | 5d | Done | Base system configuration complete | |
| 3 | Master Data Extract | MILAF | 07 Jun | 09 Jun | 3d | Done | Master data extracted from source | |
| 4 | Review Extracted Data | HITS | 09 Jun | 14 Jun | 6d | Done | Reviewed and validated | |
| 5 | Upload Reviewed Master Data | HITS | 15 Jun | 18 Jun | 4d | Done | Approved data uploaded | |
| 6 | Prepare Opening Balances | MILAF | 28 Jun | 05 Jul | 8d | In Progress | In preparation — high priority | |
| 7 | Validate Opening Balances | HITS | 05 Jul | 08 Jul | 4d | Pending | Awaiting preparation completion | |
| 8 | Upload Opening Balances | HITS | 09 Jul | 12 Jul | 4d | Pending | After balance approval | |
| 9 | Extract Open Documents | MILAF | 14 Jun | 21 Jun | 8d | Done | Open documents extracted | |
| 10 | Review Open Documents | HITS | 22 Jun | 24 Jun | 3d | Pending | Urgent review required | |
| 11 | Upload Open Documents | HITS | 25 Jun | 02 Jul | 8d | Pending | After review approval | |
| 12 | Go-Live | ALL | 15 Jul | 15 Jul | 1d | Confirmed | Confirmed once opening balances received | |
| 13 | Backlog Entry | MILAF | 15 Jul | 22 Jul | 8d | Pending | Enter backlog transactions | |
| Phase 2 | 14 | July Closing across 3 ledgers | MILAF | 31 Jul | 05 Aug | 6d | Pending | July close across 3 ledgers |
| 15 | Run Consolidation | HITS | 05 Aug | 15 Aug | 11d | Pending | Consolidate financial statements |